Professional project guide

Controls and Automation for Motorised Curtains

A controls plan defines which curtains operate individually or in groups, from which interface and under which scenarios. The control method must be compatible with the selected motor, with any lighting or home-control interface verified by the controls team.
01

Why it matters at project stage

Selecting the motor before defining controls can reveal a need for additional interfaces or expose incompatibility at commissioning. Room, façade and hours of use should inform grouping.

Motorised window treatments sit at the junction of the electrical, controls, ceiling and curtain packages. Resolving power, controls and access before finishes reduces later cable alterations, access panels and pocket revisions.

02

Information required

Document control groups, motor protocol, wall-control locations, remote functions, named scenarios, supported interfaces and commissioning responsibility.

Select motor capacity, power arrangement and control compatibility from current manufacturer information. Pile Perde identifies the window-treatment requirements for coordination but does not design the electrical installation.

03

Reaching a project decision

Independent controls may suit a simple scheme, while multiple openings can benefit from group or central commands. Base any integration on formal compatibility information for the motor and control components.

Use “Are control groups shown on the drawings” and “Are motor and protocol compatible” as decision gates for this subject. Compare any viable alternatives against those two project-specific questions, then document why the selected approach answers them.

04

Coordination through delivery

The controls team confirms addressing, scenes and the user interface; the curtain team confirms movement direction and limits. Test every treatment individually, in groups and through any central command.

Issue the motor side, power point, cable route, control group and service access as one coordinated set. Recheck any site change before commissioning.

Before handover, resolve “Are controls accessible” and “Are scenarios named clearly” with the named project parties. Record the answer under the relevant opening or room reference so a later site, material or programme revision can be assessed against the correct approval.

05

Recording and verifying the decision

For controls and automation for motorised curtains, the approval record should identify the opening or room, current drawing revision, responsible party and date. Attach the dimensions, samples or system information needed to evidence “Is the commissioning lead identified”; mark superseded decisions explicitly rather than relying on verbal instruction.

The release checklist for this guide is: Are control groups shown on the drawings; Are motor and protocol compatible; Are controls accessible; Are scenarios named clearly; Is the commissioning lead identified. Any unanswered point remains an action with a named owner and decision date, not an assumed instruction to proceed with production or installation.

Project checklist

Points to resolve in the project

  • Are control groups shown on the drawings?
  • Are motor and protocol compatible?
  • Are controls accessible?
  • Are scenarios named clearly?
  • Is the commissioning lead identified?