Professional project guide

Planning Curtain Production and Making

Release production only when the approved fabric code, final measurements, heading, draw direction and seam decisions are complete in one schedule. This connects material procurement, making and installation to the same revision.
01

Why it matters at project stage

Fabric approval alone does not remove production risk if dimensions, pattern direction or heading remain unresolved. Identify every opening separately in the workroom schedule.

02

Information required

Confirm the final sample, opening and production dimensions, heading and fullness, draw direction, usable width, pattern repeat, seams, quantities and installation sequence.

03

Reaching a project decision

Calculate fabric quantities, usable width, pattern matching and necessary seams before making. If a substitute is needed, resubmit both technical and visual differences.

04

Coordination through delivery

The workroom, project and installation teams should use the same revision schedule. Label and package completed treatments against the site opening references.

Project checklist

Points to resolve in the project

  • Is the sample final?
  • Is the measurement schedule current?
  • Are heading and direction approved?
  • Are seams defined?
  • Is installation sequence agreed?